Friday, September 23, 2011

Construction Update



New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled Completion date: 11/01/2011

Regular Construction Meeting – Monday 9:00 a.m.

Percent of Work Completed
Overall Project Completion – Construction phase 90% – the project is currently on schedule.
Irrigation – 99%
Landscaping – 95%
Concrete polishing – 95%
Roofing – 99%
Windows – 99%
Interior drywall second side – 100%
Tape & float – 99%
Prime paint – 95%
Finish paint – 25%
Interior MEP rough-in – 99%
MEP trim out – 35%
Low voltage rough-in – 99%
Low voltage trim out – 30%
Ceiling grid – 99%
Ceiling tile – 75%
Floor coverings – 85%
Kitchen equipment – 99%

Current work includes: preliminary roofing & sheet metal punch list, irrigation & landscaping,the window installation, concrete polishing, ceiling grid & tile, prime & finish painting, kitchen equipment start up, low voltage trim out, and the MEP trim out.
Two week projection includes: Installation of the gas meter, final cleaning.
The weekly Safety Meeting is held on Tuesday at 10:00 a.m.

Wednesday, September 7, 2011