New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled Completion date: 11/01/2011
Regular Construction Meeting – Wednesday at 1:00 p.m.
Percent of Work Completed
Overall Project Completion – Construction phase 60% – the project is currently on schedule.
Site utilities – 95%
Sidewalks – 95%
Concrete polishing – 30%
Roofing – 85%
Exterior plaster – 75%
Building HVAC Rough-in – 75%
Building electrical Rough-in – 75%
Building plumbing Rough-in – 85%
Building sprinkler rough-in – 65%
Masonry CMU – 90%
Masonry Brick – 65%
Windows – 55%
Interior drywall framing – 50%
Interior drywall one side – 30%
Current work includes: continuing roofing cap sheet, masonry, exterior plaster, window installation, interior drywall framing, interior drywall one siding and the MEP rough-in.
Two week projection includes: Complete installation of the electrical gear, commence second side drywall and the low voltage rough-in. Much of the site has been turned over to the landscaper and he is beginning his work.
Thursday, June 23, 2011
Subscribe to:
Posts (Atom)