Here are a few highlights of the status:
- 2 landscaping crews working - irrigation and grading/preparation teams
- will be sodding and hydramulching soon and will water the new grass as they have been watering the trees
- all the sidewalks are finished and they are caulking them as well as the parking lot pavement
- the site fencing is close to completion
- all the canopies for the bus drive and the front drive are on the site and will be up within about 2 weeks
- the Memory Brick bench has been built in the garden area to the south of the library
- 95% of the drywall work is complete
- once drywall is complete they are following with prime coats of paint and ceiling grid...they really look like rooms!
- some carpet has been laid in the the 2, 3, 4, 5 grade areas
- library furniture will be delivered in about 2 weeks
- the front tower is almost complete - needs a roof and glass
WOW! I'll be meeting soon to begin the discussion about moving plans and move in date.