Status of the Project

New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled Completion date: 11/01/2011

Percent of Work Completed
Overall Project Completion – Construction phase 85% – the project is currently on schedule.
Irrigation – 95%
Landscaping – 85%
Exterior canopies – 100%
Concrete polishing – 70%
Roofing – 99%
Windows – 99%
Interior drywall second side – 90%
Tape & float – 70%
Prime paint – 50%
Interior MEP rough-in – 95%
Low voltage rough-in – 90%
Ceiling grid – 70%
Ceiling tile – 30%
Kitchen equipment – 90%

Current work includes: continuing the roofing sheet metal, irrigation & landscaping, the window
installation, concrete polishing, interior drywall, ceiling grid & tile, prime painting, kitchen
equipment installation, low voltage rough-in, and the MEP rough-in.

Two week projection includes: Installation of the gas meter, AT&T phone lines, Comcast fiber,
and kitchen equipment start up.