New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled completion date: 11/01/2011
Regular construction meeting: Monday at 10:00 a.m.
Percent of Work Completed
Over-all Project Completion – construction phase 96%. The project is currently on schedule.
Concrete polishing – 99%
Finish paint – 99%
MEP trim out – 95%
Low voltage trim out – 90%
Floor coverings – 95%
Current work includes: Finish painting, kitchen equipment start-up, low voltage trim-out, and the MEP trim-out. Contractor punch list is being prepared.
Two-week projection includes: Installation of the gas meter, final concrete polishing, final cleaning, and start the Architect and Engineer team punch list preparation.
No comments:
Post a Comment