Friday, October 7, 2011

We have a move date!

Students will be moving in to the new school on December 12, 2011! We are so excited. To facilitate this move we will have additional early dismissal days in December. Please mark your calendars for NOON DISMISSAL on Dec 2 and Dec 15, as well as the scheduled date - Dec 16.

New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled completion date: 11/01/2011


Percent of work completed
Overall project completion: Construction phase 90%. The project is currently on schedule.
Irrigation – 99%
Landscaping – 99%
Concrete polishing – 95%
Roofing – 99%
Windows – 99%
Tape & float – 99%
Prime paint – 99%
Finish paint – 75%
Interior MEP rough-in – 99%
MEP trim out – 75%
Low voltage rough-in – 99%
Low voltage trim out – 50%
Ceiling grid – 99%
Ceiling tile – 85%
Floor coverings – 85%
Kitchen equipment – 99%

Current work includes: Preliminary roofing and sheet metal punch list, irrigation and landscaping, the window installation, ceiling grid and tile, prime & finish painting, kitchen equipment start up, low voltage trim out, and the MEP trim out.

Two-week projection includes: Installation of the gas meter, final concrete polishing, final cleaning, and start contractor punch list preparation.


No comments:

Post a Comment