New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled completion date: 11/01/2011
Percent of work completed
Overall project completion: Construction phase 90%. The project is currently on schedule.
Irrigation – 99%
Landscaping – 99%
Concrete polishing – 95%
Roofing – 99%
Windows – 99%
Tape & float – 99%
Prime paint – 99%
Finish paint – 75%
Interior MEP rough-in – 99%
MEP trim out – 75%
Low voltage rough-in – 99%
Low voltage trim out – 50%
Ceiling grid – 99%
Ceiling tile – 85%
Floor coverings – 85%
Kitchen equipment – 99%
Current work includes: Preliminary roofing and sheet metal punch list, irrigation and landscaping, the window installation, ceiling grid and tile, prime & finish painting, kitchen equipment start up, low voltage trim out, and the MEP trim out.
Two-week projection includes: Installation of the gas meter, final concrete polishing, final cleaning, and start contractor punch list preparation.