Friday, December 30, 2011

Happy New Year 2012

Happy New Year to all of the MWE Family. I hope you are enjoying your holidays and time with your families. As I write from Crested Butte, Colorado, I'm enjoying the mountains, the snow, doing a whole lot of nothing and taking my son's dogs on long walks in the beautiful sunshine and fresh mountain air.

Our first week in the new building went so quickly. The faculty and the students were so happy with the space, the light, the newness of everything and, especially, having their SPARK Park for recess. We are so excited that the library will be able to open soon after we return in January - thanks to Mrs. Clarkson and her hardworking volunteers for all their hard work.

There are still many things to be done to finish the project. Over the holidays they were going to knock out a wall or two to repair some things, get the ACTIVboard speakers up and running, do some more work on the stair landing and much, much more. As we 'live' in the building we are able to turn in punch list items to be fixed. That means the contractors will still be there. They work after kids leave and until the custodians close the building at night: 3:30-11:00 most evenings.

I can hardly wait for our Grand Opening/Library Dedication on February 2, 2012. Our PTA is planning to follow this event with Family Fun Night so we can have a wonderful afternoon and evening to celebrate our new school.
4:00-4:30 Grand Opening/Library Dedication
4:30-5:30 Tours of the building
5:30-6:30 Family Fun Night Bingo & Teachers will sell dinner for your family

I'm so happy to get 2012 off to a great start and am looking forward to a great new year.

Please forward this to former students and neighbors who may be interested.

Sunday, December 11, 2011

First Day at the New School is TOMORROW!!

First Day at Meadow Wood Elementary

Monday, December 12, 2012

Good Morning! Happy First Day in our New School!

We are moved in, getting settled and feeling real cool.


Yesterday is gone...it's over and done...

We are in our new home and ready for fun.


Good Morning! Today’s a fresh new day.

We have new things to see and new places to play.

Today you’ll be seeing all the great new spaces

And I’m thrilled to see wonder, awe and smiles on your faces.

New wood smells, new floors, new tables and desks,

New carpet and windows and all of the rest.

Our art work is hung, done by Eagles of old.

Mrs. Hampton has plans for much more, I am told.

Books on the shelves in their beautiful new home

Are screaming – come read me – come take me home.

As I walk down the halls and look all around

I see iTouches, iPads, netbooks and great sound.

The teachers worked hard to get this all ready

So get yourself going and work hard and steady.

You are all special people and only you can say

“I was there at that fabulous new school on the very first day.”


Be thankful. Feel blessed. Show your gratitude.

Take care of our building with great attitude.


It’s time to get going and get on with our day,

I’m glad you’re all here to share this very special day.

Robye Snyder December 12, 2011

Monday, November 28, 2011

Count Down to Move In

We are anxiously counting down the days until we move into the beautiful new building. This evening the SBISD Board of Trustees toured the new campus. Everything is not completely finished but they were able to see how wonderful it all looked.

We are busy getting the students prepared for the move. Our student council did a very informative voice over of a video tour filmed by Mrs. Krug. Thanks to Mrs. Krug and Mrs. Emmons for all their help with this project.

We will be showing the video to each grade level in a meeting in the next few days. We will talk with them about all the new spaces and help them visualize (that's a great reading strategy, by the way) themselves in the new school.

Take a look at the video tour. Click here.

Don't forget. School starts at the new school on Dec 12. Parents should have received their packet of information about the move, the first day, transportation, etc last Friday. Call the office if you didn't get your info.


Saturday, October 22, 2011

Latest Schedule Information

New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled completion date: 11/01/2011
Regular construction meeting: Monday at 10:00 a.m.
Percent of Work Completed

Over-all Project Completion – construction phase 96%. The project is currently on schedule.
Concrete polishing – 99%
Finish paint – 99%
MEP trim out – 95%
Low voltage trim out – 90%
Floor coverings – 95%

Current work includes: Finish painting, kitchen equipment start-up, low voltage trim-out, and the MEP trim-out. Contractor punch list is being prepared.
Two-week projection includes: Installation of the gas meter, final concrete polishing, final cleaning, and start the Architect and Engineer team punch list preparation.

Friday, October 7, 2011

We have a move date!

Students will be moving in to the new school on December 12, 2011! We are so excited. To facilitate this move we will have additional early dismissal days in December. Please mark your calendars for NOON DISMISSAL on Dec 2 and Dec 15, as well as the scheduled date - Dec 16.

New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled completion date: 11/01/2011


Percent of work completed
Overall project completion: Construction phase 90%. The project is currently on schedule.
Irrigation – 99%
Landscaping – 99%
Concrete polishing – 95%
Roofing – 99%
Windows – 99%
Tape & float – 99%
Prime paint – 99%
Finish paint – 75%
Interior MEP rough-in – 99%
MEP trim out – 75%
Low voltage rough-in – 99%
Low voltage trim out – 50%
Ceiling grid – 99%
Ceiling tile – 85%
Floor coverings – 85%
Kitchen equipment – 99%

Current work includes: Preliminary roofing and sheet metal punch list, irrigation and landscaping, the window installation, ceiling grid and tile, prime & finish painting, kitchen equipment start up, low voltage trim out, and the MEP trim out.

Two-week projection includes: Installation of the gas meter, final concrete polishing, final cleaning, and start contractor punch list preparation.


Friday, September 23, 2011

Construction Update



New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled Completion date: 11/01/2011

Regular Construction Meeting – Monday 9:00 a.m.

Percent of Work Completed
Overall Project Completion – Construction phase 90% – the project is currently on schedule.
Irrigation – 99%
Landscaping – 95%
Concrete polishing – 95%
Roofing – 99%
Windows – 99%
Interior drywall second side – 100%
Tape & float – 99%
Prime paint – 95%
Finish paint – 25%
Interior MEP rough-in – 99%
MEP trim out – 35%
Low voltage rough-in – 99%
Low voltage trim out – 30%
Ceiling grid – 99%
Ceiling tile – 75%
Floor coverings – 85%
Kitchen equipment – 99%

Current work includes: preliminary roofing & sheet metal punch list, irrigation & landscaping,the window installation, concrete polishing, ceiling grid & tile, prime & finish painting, kitchen equipment start up, low voltage trim out, and the MEP trim out.
Two week projection includes: Installation of the gas meter, final cleaning.
The weekly Safety Meeting is held on Tuesday at 10:00 a.m.

Wednesday, September 7, 2011

Saturday, August 27, 2011

Pictures from August 19th tour More on our Facebook page Meadow Wood Elementary SBISD
























Status of the Project

New Meadow Wood Elementary School: School Replacement (68314 – 2007 Bond)
Construction Team: SHW Group Architects
Satterfield & Pontikes
SBISD P.M. – M. Ashley
Project Timeline: Bid date: 6/24/2010
Board approval date: 7/27/2010
Scheduled Completion date: 11/01/2011

Percent of Work Completed
Overall Project Completion – Construction phase 85% – the project is currently on schedule.
Irrigation – 95%
Landscaping – 85%
Exterior canopies – 100%
Concrete polishing – 70%
Roofing – 99%
Windows – 99%
Interior drywall second side – 90%
Tape & float – 70%
Prime paint – 50%
Interior MEP rough-in – 95%
Low voltage rough-in – 90%
Ceiling grid – 70%
Ceiling tile – 30%
Kitchen equipment – 90%

Current work includes: continuing the roofing sheet metal, irrigation & landscaping, the window
installation, concrete polishing, interior drywall, ceiling grid & tile, prime painting, kitchen
equipment installation, low voltage rough-in, and the MEP rough-in.

Two week projection includes: Installation of the gas meter, AT&T phone lines, Comcast fiber,
and kitchen equipment start up.

Saturday, August 6, 2011

Pictures from the tour on June 3

I swipped a link from pictures from a tour a small group of us took on June 3rd. We are going again on August 11 so more pictures should follow that tour.

Thanks to Erika Wheeler for posting these on her new blog. Click Here



Friday, August 5, 2011

Landscaping at the new school

If you haven't driven by lately...
The landscaping crew has been hard at work putting in an extensive sprinkler system in ALL of the front areas of the school. We will be able to water the trees, the beds, and the garden south of the library. Our school is going to be a jewel along Memorial Drive!

They were working on finishing up the canopy work on the front drive, the bus drive and the tower yesterday. Those areas are looking great.

The building looks very close to being finished - from the outside. There are still many weeks/months of work to be done to the inside.

I'll be taking another small group of MWE staff to tour on August 11. We will take lots of pictures and post them here very soon after the tour.

If you are anywhere in the area you will certainly want to drive by. The fencing is down so you can even drive through the front drive. It's very complicated.....you can go all around the outside drive and back to the light OR part of the way in you turn left and go to the parking area OR drive all the way across the front and then turn left into the parking area OR drive all the way around the front and go straight to exit in the turn right lane OR go all the way around the front, don't turn left into the parking lot but turn left into the 'go back to the light at Clear Springs' lane OR get lost in rambling around among the trees!!!

Wednesday, July 27, 2011

Update July 27, 2011

Great meeting at the construction trailer today. I'm sure you have seen, as you drive by, that there are LOTS of workers. At the safety meeting this week there were over 140 workers signed in. They are busy, busy, busy.

Here are a few highlights of the status:


  • 2 landscaping crews working - irrigation and grading/preparation teams

  • will be sodding and hydramulching soon and will water the new grass as they have been watering the trees

  • all the sidewalks are finished and they are caulking them as well as the parking lot pavement

  • the site fencing is close to completion

  • all the canopies for the bus drive and the front drive are on the site and will be up within about 2 weeks

  • the Memory Brick bench has been built in the garden area to the south of the library

  • 95% of the drywall work is complete

  • once drywall is complete they are following with prime coats of paint and ceiling grid...they really look like rooms!

  • some carpet has been laid in the the 2, 3, 4, 5 grade areas

  • library furniture will be delivered in about 2 weeks

  • the front tower is almost complete - needs a roof and glass

WOW! I'll be meeting soon to begin the discussion about moving plans and move in date.


Sunday, July 10, 2011

Walk Through of New Building on June 3

On June 3, 2011, a small group of MWE faculty got to take a tour of the new building. I've got a few pictures and will try to help you visualize what you are seeing. We loved the flow and the openness of the inside. It is going to be beautiful.Here we are in the construction trailer office getting ready to go. We had to wear hard hats and safety goggles. It was fun and hot, hot, hot!!


We started off across the covered hard top to the north of the gym...that's the gym you see with the square windows. Notice the basketball goals already up on the covered hard top. There will be doors out of the back of the gym to lead to this area. Thrower Park has been reinstalled on the other side of the covered hard top - the small red play area dedicated to former Health Fitness teacher Connie Thrower.





Here we are leaving the gym and walking into the
large hallway area that allows the art room, music rooms (yes, 2 rooms) and the gym to be close to each other and all under a roof. The gym looks basically the same but is being refurbished. The
corner where we used to enter and the gym office were demolished as that is the portion that will join to the new building. The office will be on the other end of the gym. Restrooms remain the same.



We are outside the gym in front of the music
rooms. The stairs to the left will be in the music room and will lead to the back of the stage. Cool -
backstage access!!

The wall studs to the right are the walls of the art room. You can see the stairs in the distance.








Here is the stairway in the main corridor. Notice at the bottom there is a platform. This platform surrounds the bottom and goes under a bit to tie it all together. Of course, there will be rails where there are not walls and there will be a rail at the top balcony. Don't think flimsy home type rails but taller than usual and almost solid at the top balcony. It's hard to explain until you see it.

The room beyond the stairs is the science lab.
The area to the right is 2nd and 3rd grade and at the top of the stairs is 4th and 5th grades.



In this view we are standing across from the
stairs in the main corridor in front of the cafeteria
walls - the large studs on the far left. The opening to the outside is the bus drive and faculty parking lot entrance. The small door in the studs is the faculty lounge and the large opening are the 'cafeteria restrooms'.









We then went upstairs to the 4th/5th grade area. This is an adult restroom that shows the 3 colors we are using throughout the building. Each area will be a different color in the hallways and as accents in the classrooms and counter tops.









This is the outside area of the 5th grade restrooms. The sink and water fountains will be in this common area and then you'll go to the right or left into the girls' or boys' restroom areas...no doors. Don't worry. It's very private and very easy for teachers to monitor this way. We can't wait for the new bathrooms. Funny what makes us happy!!








This is a classroom. It is a fifth grade room that looks out toward the gym but all the rooms are the basically the same...3 windows, 4 walls, high ceilings....wonderful!!! I'm standing pretty far into the room so you don't get a sense of the size. We all thought it felt large.









We went down the back stairway that faces SFMS, turned left and then left again and head back inside. The sidewalk we are on goes out to the playground area behind us and ahead of us leads into the main corridor right by the library. To the left is the two story 2nd/3rd & 4th/5th wing and to the right is the 1st grade/special ed wing. This courtyard area is going to be a place for us to plant butterfly, hummingbird and vegetable gardens. We hope to partner with Urban Harvest. What a wonderful outdoor learning space.

The area you see in front of us that connects the two wings is a deep covered porch and a glass wall. This is part of the main corridor directly across from the library.


The two square post will be the wall of glass and doors that comes in from the sidewalk off the porch into the large open 'mall' area in the main corridor. From this view we are looking straight out the front of the school (the light in the distance). The studs mid picture are the back part of the administrative office and workroom. That square window will be in the principal's office to look out and see down the main corridor (YEAH!!!). To the left, not in this picture, is the library.


The next three pictures are of the library. Notice the beautiful wood ceiling. Those beams came all the way from Oregon. The far wall will be limestone inside and out with the 3 big windows.



Beautiful wooden ceiling!!



Kindergarten building. Same room configuration, less windows - the better to prevent leaks!!

This is the front foyer area. I'm looking out the front door area...standing where the hallway goes off to the right for the first grade/special ed wing and to the left is the back of the administrative area.

This is the exit from the end of the kindergarten building to the playground. The large Texas Mosaic will be going right to the left of this entrance.
THE END!!!